Williamson County Schools held a ribbon-cutting ceremony on August 10, 2025, to commemorate the completion of Brentwood Middle School’s new facility.
The event marked the end of a two-phase construction project to recapitalize the Brentwood Middle School property.
Phase 1 began in 2022 and included demolishing a portion of the existing school along Granny White Pike and replacing it with a new cafeteria, gymnasium, and related arts area, along with a three-story, 36-classroom addition and media center.
Phase 2 demolition began in June of 2024. This phase included the demolition of the remainder of the existing building as well as the construction of a three-story wing containing 36 classrooms and a multi-purpose field.
Now that the project is complete, the new Brentwood Middle facility has 72 classrooms to serve students.